• According to National Electric Code, at least 3ft. (914mm) clearance in the front and rear of the UPS is required
for installation and maintenance, see Figure 3.1 below. No side clearance is required.
• During operation, 8 in.(203mm) rear clearance is required, unless the unit includes the optional POD, then 3ft.
(914mm) rear clearance is required.
• If a top fan is installed and there is no POD, rear clearance is not required.
Figure 3.1 Installation and Maintenance Clearances
Item Description
1 No side clearance required
2 UPS (top view)
3 No side clearance required
4 Wall or other solid surface
18 Proprietary and Confidential ©2023 Vertiv Group Corp. 3 Installation and Commissioning