NOTE!
The operator is obliged to ensure, that the installation of the water purification unit and its
operation are carried out in compliance with all national and international guidelines,
applicable and valid for the place of installation.
If necessary, measures to protect the drinking water have to be taken by installing
appropriate components.
Take the following criteria into consideration when selecting the installation area:
Feedwater pressure (potable tap water) not less than 1 bar (14 PSI) and not greater than 6 bar (87 PSI).
CAUTION
The feedwater pressure must not be allowed to go above 6 bar. Install an additional pressure
reducer when the feedwater pressure is higher.
Minimum air temperature +2 °C
The surface on which the system is installed must be level and stable not to exceed a
maximum of 2% deviation from evenness is recommended.
A smooth wall is required when the system is to be wall-mounted. Check the statics of
the wall or standing surface. The standing or wall surface must be strong enough to hold
the system. (for system weight, see “Accessibility to Puranity TU+ systems and pure
water tank” on page 17).
CAUTION
Free gravity flow to drain must be ensured.