Transport
Boiler/straticationcylinder
- The boiler and the stratication cylinder are transported, fully packaged, on a pallet
- A sack truck is a suitable means of transportation
- Position the sack truck behind the boiler or stratication cylinder, secure with a strap
and transport to the installation location
The COB and TS are installed adjacent to the wall, which means that a clearance of
70 cm only needs to be observed at the front. When installing the boiler, you should
observe the recommended wall clearances in order to simplify assembly, maintenance
and servicing.
Recommended minimum
wall clearance
Installation information
- Install the boiler or boiler plus DHW cylinder on a level
surface which is substantial enough to carry its weight.
- Level the boiler and stratication cylinder horizontally using
adjustable feet.
Adjustable feet
- Remove strap and packaging
- Remove the four xing screws on the pallet
- Lift the boiler and/or stratication cylinder off the pallet
COB with
TS behind
- The boiler must only be installed in a room that is protected from frost.
Drain the boiler, stratication cylinder and heating system if there is a risk
of frost when the system has been shut down.
- Boilers should not be installed in a room that is subject to aggressive vapours
or in very dusty or highly humid conditions (workshops, washrooms, hobby
rooms, etc.).
- The combustion air must be free from halogenated hydrocarbons.
- A surface temperature of 40 °C is not exceeded in the case of COB if
operated as intended. The respective national re regulations are to be
observed in the case of installation in oil storage rooms.
NB
NB
NB
COB with
TS right
or left
COB-40
minimum
room height
COB
70 cm 70 cm
70 cm
70 cm
70 cm
190 cm