52 Installation and Operating Instructions V03
Check the grid voltage: check that the grid voltage at the point of connection of
the inverter complies with the permitted value.
8.2 Mechanical checks
Carry out the main mechanical checks to ensure the inverter is waterproof:
Make sure the inverter has been correctly mounted with wall bracket.
Make sure the cover has been correctly mounted.
Make sure the communication and AC cable gland has been mounted properly and
adequately locked.
Danger to life due to the presence of AC voltage
• Only touch the insulation of the AC cables.
• Wear personal protective equipment such as insulating gloves.