3.2.Operation procedures
Table 3-1 Operation procedures
Check the power supply, liquid waste connection, reagent &
sample probe/stirring rod, wash buffer remaining. Substrate
remaining, number of cuvettes, remaining capacity of solid
waste container.
Turn on the power switch and launch the operating software.
3. Confirm your
analyzer status
Check the system status, alarm status, reagent/calibration status
and maintenance status.
4. Preparation of
reagent and wash
buffer
Prepare reagent and wash buffer.
Request calibration item, prepare calibrator, start calibration test.
QC test request, prepare the control, and start the QC test.
Routine sample test request, prepare samples, and start sample
test.
Start testing the requested item.
Stop testing the requested item.
Clean the reagent & sample tray, analyzer panel, etc.
Perform the shutdown operation.
3.3.Checking before analyzer start up
3.3.1.Check power supply
1) Check the power supply, confirm that the power supply can provide the correct
voltage;