Electrical installation 73
Installing power and ground cables
Further information
See ACS580MV Base frame & TEU layout design for information on:
• Project-specific cable entry
• Distance between the point of cable entry and the termination bars
• Busbar and fastening hole dimensions
• Busbar designations
See ACS580MV Wiring Diagram for information on:
• Conventions for cross-references and device identification
Preparing the cable entry and the cables
Determining the cable length
1 Determine the required length of a cable between the point of entry and the connection
point inside the cabinet.
2 Cut the cable to the required length before connection.
Preparing cables for entry plates
• Prepare the cable termination as illustrated in the figure below.
NOTICE
Risk of damage or malfunction!
Waste inside the cabinet can cause damage or malfunction.
If possible, do not cut cables inside the terminal compartment. Retrieve any waste which
accidentally dropped into the cabinet.