88 Installation checklist
Motor
Power cables
2. High voltage connections completed
3. MCB ready to be tested with drive
4. MCB interposing relay settings tested
5. Local close order is disabled, and the connection to switch or button is canceled.
6. The wiring of the control & signal cables connecting with the converter is finished.
7. Safety devices checked and in operation
8. The user manual and technical specification is available.
9. Withstand voltage test of the MCB have been done according to Manufacture`s specifications.
The official test report must be available.
1. Motor installed, aligned and alignment protocol available
2. Motor decoupled from driven load
3. Ground connection completed
4. Customer side motor protection set and ready (e.g. winding temperature, vibration)
5. Motor auxiliaries (e.g. bearing lubrication, heater cooling) ready
6. The user manual and technical specification is available.
1. All cable screens are connected. Please take the photo and send back.