Procedure
1. Do a check on the sensors (A) that
record the shocks during transport.
2. Do a check on the sensors (B)
that record the maximum tilt during
transport.
3. If the sensors (A) show a red
indication or the sensors (B) show a
tilt that is too high, do these steps:
For the transport specifications, refer
to section 12.7.
a. Accept the delivery of the EVSE.
b. Make a note on the delivery
receipt.
c. If damage occured, leave the item
in its original packaging and request an immediate inspection from the
carrier within the applicable time period.
TiltWatch PLUS
TiltWatch PLUS
ShockDot
WARNING
ShockDot
WARNING
A
B
Transport, handling and unpacking
34 HVC 200/300/360-EN | 002

Table of Contents

Related product manuals