EasyManua.ls Logo

ABB RELION 670 SERIES REG670 - Page 364

ABB RELION 670 SERIES REG670
830 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Example for time coordination
Assume two substations A and B directly connected to each other via one line, as
shown in the Figure 176. Consider a fault located at another line from the station B.
The fault current to the overcurrent protection of IED B1 has a magnitude so that the
overcurrent protection will start and subsequently trip, and the overcurrent protection
of IED A1 must have a delayed operation in order to avoid maloperation. The sequence
of events during the fault can be described using a time axis shown in Figure 176.
A1 B1
Feeder
Time axis
t=0 t=t
1
t=t
2
t=t
3
The fault
occurs
Protection
B1 trips
Breaker at
B1 opens
Protection
A1 resets
en05000205_ansi.vsd
51
51
ANSI05000205 V1 EN-US
Figure 176: Sequence of events during fault
where:
t=0 is when the fault occurs
t=t
1
is when protection IED B1 and protection IED A1 start
t=t
2
is when the trip signal from the overcurrent protection at IED B1 is sent to the circuit breaker.
t=t
3
is when the circuit breaker at IED B1 opens. The circuit breaker opening time is t
3
- t
2
t=t
4
is when the overcurrent protection at IED A1 resets. The protection resetting time is t
4
- t
3
.
To ensure that the overcurrent protection at IED A1 is selective to the overcurrent
protection at IED B1, the minimum time dif
ference must be lar
ger than the time t
3
.
There are uncertainties in the values of protection operation time, breaker opening time
and protection resetting time. Therefore a safety margin has to be included. With
normal values the needed time difference can be calculated according to Equation
179.
Section 9 1MRK 502 071-UUS A
Current protection
358 Generator protection REG670 2.2 ANSI and Injection equipment REX060, REX061, REX062
Application manual

Table of Contents

Related product manuals