Chapter 1 9
Agilent 4072/4073 Preinstallation Guide, Edition 4
General Information
Installation Overview
Figure 1-2 Flowchart for preinstallation
START
preparing installation location
preparing for electrical equipment
confirming environmental
considerations
confirming safety precautions
preparing the requirement to connect
testhead to wafer prober
unpacking
moving to installation location
installation by Agilent CE
END
site preparation
confirming plan for site verification
checking the contents
site
verification
deciding receive day and install day
chapter 2
chapter 4
chapter 3
assigning system administrator
delivery day
installation
1 month
before delivery
customer
customer or
Agilent CE
Agilent CE
customer and
Agilent CE
2 weeks
before delivery
moving to
installation location