11.2.2 Storage times
Additional measures must be taken on commissioning to preserve proper
functioning – irrespective of the storage time which may be longer than the
warranty period of our products. However, this does not involve any
additional warranty claims.
Motors
Bearing time / months
Measures for commissioning
> 1 > 12 > 60
■ ■ ■ Visual inspection of all parts to be damage-free
■ ■ ■ Resurface the holding brake
■ ■
Check the electric contacts to verify that they are free from
corrosion
■ ■
Let the motor run in without load for one hour at 800 ...
1000 rpm
■ ■
Measure insulation resistance. Dry the winding at a value
of < 1kOhm per volt rated voltage.
■ Exchange bearings
■ Exchange encoders
Tab. 11-5: Measures before commissioning motors that have been stored over
a prolonged period of time
Cables and Connectors
Bearing time / months
Measures for commissioning
> 1 > 12 > 60
■ ■ ■ Visual inspection of all parts to be damage-free
■ ■
Check the electric contacts to verify that they are free from
corrosion
■
Visually inspect the cable jacket. Do not use the cable if
you detect any abnormalities (squeezed or kinked spots,
color deviations, ...).
Tab. 11-6: Measure before commissioning cables and connectors that have
been stored over a prolonged period of time
DOK-MOTOR*-MSK*EXGIIK3-PR09-EN-P Bosch Rexroth AG 143/175
Synchronous Servomotors MSK For Potentially Explosive Areas
Transport and storage