6 Operation
Pos: 111 /200 Chris t/360 GT-B A Labor-Pilot ( STANDARDMOD ULE)/060 Be trieb/060-0010 Erste Inbetrieb nahme Labor++++ +++++++ ++++++ +++++++++ @ 25\ mod_140498 3760674_68.doc x @ 183592 @ 2 @ 1
6.1 Initial start-up
Before the initial start-up, please ensure that your freeze-dryer is properly
set up and installed (see chapter 5 - "Set-up and connection")
Pos: 112 /010 Uni versalmodule/ Leerz eile @ 0\mod_12 02116244500 _0.docx @ 1 14 @ @ 1
Pos: 113 /010 Uni versalmodule/ Leerzeile @ 0\mod_12 02116244500 _0.docx @ 1 14 @ @ 1
Pos: 114 /200 Chris t/360 GT-B A Labor-Pilot ( STANDARDMOD ULE)/060 Be trieb/060-0020 Installation vo n Zubehörko mponenten+++++++ ++++++ +++++++ ++ @ 25\mod_14049837 61840_68.doc x @ 183607 @ 2 @ 1
6.2 Installation of accessories
The accessories must be completed in accordance with the drying method
that is applied as well as in accordance with the scope of supply.
Please contact our sales department if you have any queries.
Pos: 115 /010 Uni versalmodule/ Leerzeile @ 0\mod_12 02116244500 _0.docx @ 1 14 @ @ 1
Pos: 116 /010 Uni versalmodule/ Leerzeile @ 0\mod_12 02116244500 _0.docx @ 1 14 @ @ 1
Pos: 117 /200 Chris t/360 GT-B A Labor-Pilot ( STANDARDMOD ULE)/060 Be trieb/060-0030 Vorbereitung der Gefriertr ocknungsanlage +++ +++++++ ++++++++++ ++++++++++ +++ @ 25\mod_140 4983762863_ 68.docx @ 183620 @ 2 @ 1
6.3 Preparation
The ice condenser chamber must be clean and dry.
• Remove any water residues from the preceding run.
• Close the media drain valve and the aeration valve.
• Ensure that all of the valves of the accessories are closed.
• Switch the vacuum pump on.
Pos: 118 /010 Uni versalmodule/ Leerzeile @ 0\mod_1 202116244500 _0.docx @ 1 14 @ @ 1
Pos: 119 /010 Uni versalmodule/ Leerzeile @ 0\mod_12 02116244500 _0.docx @ 1 14 @ @ 1
Pos: 120 /200 Chris t/360 GT-B A Labor-Pilot ( STANDARDMOD ULE)/060 Be trieb/060-0040 Einschalten ( nur Netzschalter) ++++++++ +++++++ +++++++++++++ ++++++++++ @ 25\mod_140498376 4944_68.docx @ 183648 @ 2 @ 1
6.4 Switching the freeze-dryer on
• Actuate the mains switch.
The control unit performs a self-test and an initialisation. This may take
several seconds.
• Follow the safety instructions and hazard warnings (see chapter 3 -
"Safety")!