2 Components
Service manual
63
EBLQ+EDLQ011~016CAV3+W1 + EBLQ+EDLQ011~016CA3V3+W1
+ EK(2)CB07CAV3 + EKMBUHCA3V3+9W1
Daikin Altherma – Monobloc
ESIE18-04 – 2019.02
a HAP LED
Does the HAP LED blink in
regular intervals (1second
ON/1second OFF)?
Action
Yes Return to "Checking
procedures"on page62 of the
inverter PCB and continue with
the next procedure.
No Replace the inverter PCB, see
"Repair procedures"on
page64.
To check if the correct spare part is installed
1 Visit your local spare parts webbank.
2 Enter the model name of your unit and check if the installed
spare part number corresponds with the spare part number
indicated in the webbank.
Is the correct spare part for the
inverter PCB installed?
Action
Yes Return to "Checking
procedures"on page62 of the
inverter PCB and continue with
the next procedure.
No Replace the inverter PCB, see
"Repair procedures"on
page64.
To check the wiring of the inverter PCB
1 Check that all connectors are fully plugged‑in. All colour codes
MUST correspond.
2 Check that no connectors are damaged.
3 Check that the wiring corresponds with the wiring diagram, see
"5.2Wiring diagram"on page101.
Is the wiring on the inverter
PCB correct?
Action
Yes Return to "Checking
procedures"on page62 of the
inverter PCB and continue with
the next procedure.
No Adjust the wiring of the inverter
PCB, see "Repair procedures"on
page64.
To perform an electrical check of the inverter PCB
Prerequisite: Turn OFF the unit via the user interface.
Prerequisite: Turn OFF the respective circuit breaker.
Prerequisite: Remove the required plate work, see "2.19 Plate
work"on page77.
1 Open the compressor insulation.
2 Measure the voltage on the inverter PCB between TP1 and
TP2. Wait until the voltage drops below 10VDC.
WARNING
The smoothing capacitor MUST discharge below 10VDC
before disconnecting the Faston connectors from the
compressor wiring terminals. Risk of electrocution.
3 Disconnect the Faston connectors from the compressor wire
terminals U, V and W.
INFORMATION
Note the position of the Faston connectors on the
compressor wire terminals to allow correct connection
during installation.
4 Connect the Faston connectors to the Inverter Analyzer (SPP
number 1368521).
5 Turn ON the power of the unit.
6 Locate the LEDs on the inverter PCB. The LED status should
be as follows:
a H1P
b H2P
c H3P
d H4P
e H5P
f H6P
g H7P
LED OFF
LED ON
LED blinking
7 Locate the switch BS1 on the Inverter Analyzer and press for
5seconds to activate the inverter test. The LED status should
be as follows:
8 Press the switch BS2 twice. The LED status should be as
follows: