培训手册 Training Manual
操作前检查 Pre-operation Inspection
JCPT- DCS
www.cndingli.com
3-8
⊙ 结果:机器应按照控制面板上向下箭头所指示的方向移动,然后突然停止。(Result: The
machine should move in the direction that the yellow down arrow points on the control panel,
then come to an abrupt stop.)
注意:刹车必须能够使机器在能够攀爬的任何坡度上停稳。
Note: The brakes must be able to hold the machine on any slope it is able to climb.
测试限制的驱动速度(Test Limited Drive Speed)
35) 按下起升功能选择按钮,指示灯亮。按住控制手柄上的功能启用按钮,升起平台到距离地面约
2m 高度。(Press and hold the lift function enable switch. Raise the platform approximately
2m from the ground.)
⊙ 结果:坑洞保护装置展开。(Result: The pothole guards should deploy.)
36) 按下驱动功能选择按钮,指示灯亮。(Press and hold the function enable switch on the
control handle.)
37) 按住控制手柄上的功能启用按钮,缓慢移动控制手柄至完全驱动位置。(Slowly move the
control handle to the full drive position.)
⊙ 结果:平台升起状态下最大驱动速度不应超过 20cm/s。(Result: The maximum achievable
drive speed with the platform raised should not exceed 20cm/s.)
¤ 结果:平台升起状态下最大驱动速度超过 20cm/s,请立即标记机器。并停止运行。(Result: If
the drive speed with the platform raised exceeds 20cm/s, immediately tag and remove the
machine from service.)
测试倾斜传感器操作(Test the Tilt Sensor Operation)
注意:在地面上用平台控制器进行该项测试。不要站在平台里面。
Note: Perform this test from the ground with the platform controller. Do not stand in the platform.
38) 完全降下平台。(Fully lower the platform.)
39) 将一侧的两个轮驱动到一个 3.5×20cm 的垫块上。(Place a 3.5×20cm or similar piece of
wood under both wheels on one side and drive the machine up onto them.)
40) 将平台起升至少 2m。(Raise the platform at least 2m.)
⊙ 结果:平台应停止运动,同时倾斜警报应每分钟鸣响 150 次。(Result: The platform should
stop and the tilt alarm will sound at 180 beeps per minute.
)
41) 按照向上箭头指示的方向移动驱动控制手柄,然后再按照向下箭头指示的方向移动。(Move
the drive control handle in the direction indicated by the blue up arrow, then move the drive
control handle in the direction indicated by the white down arrow.)
⊙ 结果:驱动功能在任一方向上都不应工作。(Result: The drive function should not work in
either direction.)