5 Commissioning
5.1 Switching on the measuring device
On completion of the installation (successful post-installation check), wiring (successful
post-connection check) and after making the necessary hardware settings, where applicable, the
permitted power supply (see nameplate) can be switched on for the measuring device.
When the power supply is switched on, the measuring device performs a number of power-up
checks and device self-checks. As this procedure progresses the following messages can appear
on the local display:
The measuring device starts operating as soon as the startup procedure is complete.
Various measured values and/or status variables appear on the display.
!
Note!
If an error occurs during startup, this is displayed by an error message. The error messages that
occur most frequently when a measuring device is commissioned are described in the
Troubleshooting section → ä 26.
Display examples:
Name of the measuring device
START-UP
RUNNING
Start-up message
Æ
Name of the measuring device
DEVICE SOFTWARE
V XX.XX.XX
Displays the current software
Æ
SYSTEM OK
→ OPERATION
Beginning of operation