EPSON Stylus PHOTO 895/785EPX Revision A
Disassembly and Assembly Overview 71
4.1.3 Work Completion Check
If any service is made to the printer, use the checklist shown below to confirm all
works are completed properly and the printer is ready to be returned to the user.
Table 4-2. Completion Check
Classifi-
cation
Item Check Point Status
Main Unit Self-test Is the operation normal?
Checked
Not necessary
On-line Test Is the printing successful?
Checked
Not necessary
Printhead Is ink discharged normally from
all the nozzles?
Checked
Not necessary
Carriage
Mechanism
Does it move smoothly?
Checked
Not necessary
Is there any abnormal noise
during its operation?
Checked
Not necessary
Is there any dirt or foreign
objects on the CR Guide Shaft?
Checked
Not necessary
Is the CR Motor at the correct
temperature?
(Not too heated?)
Checked
Not necessary
Paper Feeding
Mechanism
• Is paper advanced smoothly?
• No paper jamming?
• No paper skew?
• No multiple feeding?
• No abnormal noise?
Checked
Not necessary
Is the PF Motor at correct
temperature?
Checked
Not necessary
Is the ASF motor at correct
temperature?
Checked
Not necessary
Is the paper path free of any
obstructions?
Checked
Not necessary
Adjustment Specified
Adjustment
Are all the adjustment done
correctly?
Checked
Not necessary
Lubrication Specified
Lubrication
Are all the lubrication made at
the specified points?
Checked
Not necessary
Is the amount of lubrication
correct?
Checked
Not necessary
Function Printer
Firmware version
Version:
Checked
Not necessary
Printon
Firmware version
Version:
Checked
Not necessary
Packing Ink Cartridge Are the ink cartridges installed
correctly?
Checked
Not necessary
Protective
Materials
Have all relevant protective
materials been attached to the
printer?
Checked
Not necessary
Others Attachments,
Accessories
Have all the relevant items been
included in the package?
Checked
Not necessary
Table 4-2. Completion Check (continued)
Classifi-
cation
Item Check Point Status