Appendix 3: FHP Non-Export compliance
mode for solar and BESS utility programs.
Generally, The commissions in USA request the suppliers of solar and BESS equipment listed and comply with the rules of the
interconnection of distributed generating facilities.
Non-export compliance is built in the BESS work mode setting, such as HECO CSS, NEM+ program, and California States
Commission's NEM non-export program.
FHP aPower equipment has an advanced inverter to control the non-export to zero while the non-export function is enabled. And
the solar non-export will be enabled also.
Franklin APP provides the work mode to installer setting up.
Once the program with non-export is activated in the “FranklinWH” APP, the FHP system will automatically run the pre-setting
“non-export” built-in function according to the compliance and management there is no power export to the grid.
1), When the FHP system detects that the export current is over zero, the aPower unit will dynamically absorb the excess power
generated from solar to balance the current export is zero.
2), The relay for solar input will be automatically disconnected within 2 seconds, if
The aPower unit can’t balance the export current value to zero within 30 seconds.
The aPower unit is fully charged and the export current could not be balanced to zero within 30 seconds.
Figure Example of a work mode for a program HECO CSS with non-export built-in.