74
Test Procedu-
re
(continued)
- Next, the display will show „SYNC
AC
,“ the grid icon will blink
5. Startup test
- Before the Fronius IG Plus begins feeding power into the grid, grid
conditions are tested according to local regulations
- ‘STARTUP’ will appear on the display
6. Grid power feed-in
- Once the tests have been completed the Fronius IG Plus starts
feeding power into the grid
- The display shows the current power feeding into the grid
- The Operating Status LED is illuminated green and the Fronius IG
Plus is in operation
The startup test can take anywhere from just a few seconds up to
several minutes depending on local regulations. Progress is indicated
by a vertical segment bar which reduces in size from top to bottom.
Two of the previously flashing dividing marks disappear for every 10%
of the total duration of the startup test that has been completed.
4. Only for the Italy country setup (ITA setup): Auto test
- The Fronius IG Plus tests the grid monitoring function
- The display alternates between ‘AUTOTEST’ and ‘AUTOOK’