EP18-72-IOMM-2015-7
Fulton Ltd
Page 30
MAINTENANCE - 4
4.5 BOILER INTERNAL INSPECTION
The boiler elements should be removed (see Section 4.4.1 Element Removal) after one month
of operation and the interior of the boiler thoroughly examined. If scale or sludge build-up is
observed, it should be removed and the water treatment supplier advised.
Newgasketsmustbettedeverytimeanelementisremoved.Subsequentinteriorexaminations
should be carried out on a regular basis until satisfactory conditions are observed. Thereafter,
inspections should be carried out at three monthly intervals.
Figure. 15 - Boiler Inspection Hole
Boiler heating
element
Boiler heating
element removed to
reveal inspection hole
4.5.1 FEEDWATER TANK INTERNAL INSPECTION
Figure.16-Feedwater Tank Inspection Door
Isolate the boiler electrics at the isolator on the front access panel and remove the boiler top
access panel.
Open the feedwater tank access door and check the tank is clean and clear of obstruction.
Drain the tank and clean as necessary (see Section3.6-DrainingtheFeedwaterTank).
Boiler water level
probes
Feedwater tank
access door