EasyManuals Logo

GE BrightSpeed Elite User Manual

GE BrightSpeed Elite
170 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #86 background imageLoading...
Page #86 background image
GE HEALTHCARE
D
IRECTION 5141177-100, REVISION 14 BRIGHTSPEED ELITE, EDGE, EXCEL: PRE-INSTALLATION
Page 86 Section 8.0 - Structural Requirements
8.5.3 Equipment Location
To minimize the interference, the CT equipment should be placed on a solid floor, located as far as
possible from the following vibration sources:
8.6 Walls: Scan Window
The recommended patient viewing window dimensions are 1219 mm wide by 1067 mm high (48 in.
x 42 in. ). The location of the window is dependent on the position of Operator Workspace position.
Consult Section 10.0 of this chapter and a qualified radiological health physicist for radiation
protection requirements of glass (lead content and thickness).
Note: The operator at the Operator Workspace must be able to view the patient during a scan.
8.7 Ceiling Requirement
The weight of "Boom in a room LCD monitor" assy is 50 kg., and ceiling shall have enough strength
against the specification.
Parking lots Roadways Subways
Trains Hallways Elevators
Heliports Hospital power plants containing pumps, motors, air handling
equipment and air conditioning units

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE BrightSpeed Elite and is the answer not in the manual?

GE BrightSpeed Elite Specifications

General IconGeneral
BrandGE
ModelBrightSpeed Elite
CategoryMedical Equipment
LanguageEnglish

Related product manuals