10.5.2 Top cable entry box
Fig. 10.5.2-1 Top cable entry box assembly
In case the power cables enter the UPS cabinet by the top, an optional “Top Cable Entry Box” must be
provided:
• Remove the bottom grid “A” from the left side of the UPS cabinet.
• Locate the piece “B” against the left side of the UPS cabinet and hook it up to the slits at the top of
the UPS cabinet.
• Drill the removable cover “D” with appropriate hole and install the cable glands (not provided with
the equipment).
• Run the power cables through the cable glands, feed them through the aperture at the bottom of
the UPS cabinet and connect them to the input/output terminals.
• Fix the side cover “C” and the top cover “D” using the screws fitted on both sides.
If the UPS is equipped with optional “5
th
Harmonic Input Filter or 5
th
+ 11
th
Harmonic Input Filter”
cabinet, the “Top Cable Entry Box” must be installed against the left side of the filter cabinet.
If the UPS is equipped with additional cabinets, the optional “Top Cable Entry Box” must be installed