3.2.3 APPLICATION NOTES
3.2.3.1 SETTING GUIDELINES
Following changes on the network caused by faults or other operational requirements, it is possible that various
subsystems will be formed within the pow
er network. It is likely that these subsystems will suffer from a
generation/load imbalance. The "islands" where generation exceeds the existing load will be subject to
overfrequency conditions. Severe over frequency conditions may be unacceptable to many industrial loads, since
running speeds of motors will be affected. The overfrequency element can be suitably set to sense this
contingency.
P64x Chapter 12 - Frequency Protection Functions
P64x-TM-EN-1.3 261