Plan 3 Lifting:
1> Unpack the WIT Inverter (remove the top panel and the support plates) and pull out the
handles, as shown in Fig 5.8 below. It requires four people to lift the WIT Inverter and move it to
the installation position;
2> Keep balance when lifting and moving the WIT Inverter.
Fig 5.8 Lifting the WIT inverter
5.4 Mounting the WIT Inverter
5.4.1 Ground-mounted Installation
The WIT 50-100K Storage/Hybrid Inverters can be installed on the ground. Determine the hole
positions using the marking-off template and drill holes into the ground. Insert nuts (φ12) into the
ground, and then place the inverter in the correct position and tighten the screws. The dimensions
of the marking-off template are shown in Fig 5.9.
Fig 5.9 Floor-mounted installation hole positions
Refer to figure 5.10 for floor-mounted installation.