6.6 Post-installation Checks
The following table lists the post-installation items to be checked:
Ground cable connected
to the chassis
Check the cable specifications; ensure that the cable has been
securely fastened
Ground cable on the AC
side
Check the cable specifications; ensure that the cable has been
securely fastened
Grid side
(-AE/-AU/-HE/-HU)
Check the cable specifications; ensure that the cable has been
securely fastened
Check the cable specifications; ensure that the cable has been
securely fastened
No gap exists; the fireproof mud has been evenly applied
Install the cover after the items on the AC side are checked
Ground cable on the PV
side
Check the cable specifications; ensure that the cable has been
securely fastened
Check the cable specifications; ensure that the cable has been
securely fastened; confirm that the number of PV modules
matches the rated power
Ground cable on the
battery side
Check the cable specifications; ensure that the cable has been
securely fastened
Ensure that the positive and negative terminals are connected
correctly and securely; the sealing rubber ring is properly seated
into the gland
Ensure that the connection is correct and secured; the sealing
rubber ring is properly seated into the gland
The cables are bundled in the specified position
Ensure that the connection is correct and secured; the sealing
rubber ring is properly seated into the gland
Ensure that the connection is correct and secured; the sealing
rubber ring is properly seated into the gland
Ensure that the connection is correct and secured; the sealing
rubber ring is properly seated into the gland
Ensure that the connection is correct and secured; the sealing
rubber ring is properly seated into the gland
Ensure that the connection is correct and secured; the sealing
rubber ring is properly seated into the gland
Reinstall the right cover plate after all the items are checked.