III. Installation: Foundation, Vibration, Elevation, Clearances,
Transportation
Foundation
The chiller must be installed on a level concrete foundation, level roof curb, or level perimeter
beam system.
Comply with local codes for proper anchoring and vibration isolation.
Use of a level roof curb or perimeter beam system requires the specifying engineer to identify
all necessary materials of construction, thickness, and additional bracing or supports.
See the diagrams below for mounting hole locations.
Point load at each mounting location is 200 lbs. or less.