• The components included with the hardware option kit
• T-10 Torx screwdriver
• T-15 Torx screwdriver
• Additional cables, as needed. For more information, see SFF cables on page 142.
• NVMe drives
For more information, contact a Hewlett Packard Enterprise authorized reseller.
Procedure
1. Back up all server data.
2.
Power down the server on page 31.
3. Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
4.
Do one of the following:
a.
Extend the server from the rack on page 31.
b.
Remove the server from the rack on page 32.
5.
Remove the access panel on page 32.
6.
Use a T-10 Torx screwdriver to remove the universal media bay blank.
7. Use a T-10 Torx screwdriver to install the 2 SFF NVMe drive cage.
Hardware options installation 71