Huawei FusionServer Pro 2288H V5 - Installing a Server on Holding Rails

Huawei FusionServer Pro 2288H V5
177 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Step 5 Check indicator status.
For details, see 2.1.2 Indicators and Buttons.
----End
7.2.5.2 Installing a Server on Holding Rails
For details, see 7.2.4.3 Installing Holding Rails.
Procedure
Step 1 Install the server.
NO TICE
At least two people are required to move the device. Otherwise, personal injury or device
damage may occur.
1. Pull out the inner rails as far as they will go.
Figure 7-9 Pulling out an inner rail
2. Lift the server (at least two people are required), align the nail heads on the server with
the L-shaped cutouts on the inner rails, and push the server until it clicks into position.
See (1) and (2) in Figure 7-10.
FusionServer Pro 2288H V5 Server
User Guide
7 Installation and Configuration
Issue 08 (2019-10-30) Copyright © Huawei Technologies Co., Ltd. 82