8 Maintenance
Prerequisites
● Wear personal protective equipment and use dedicated insulated tools to avoid
electric shocks or short circuits.
● Before performing maintenance, power o the equipment, follow the
instructions on the delayed discharge label, and wait for a period of time as
specied to ensure that the equipment is not energized.
8.1 SUN2000 Power-O
Important Notes
● After the system is powered o, the inverter is still energized and hot, which
may cause electric shocks or burns. Therefore, wait for 5 minutes after power-
o and then put on insulated gloves to operate the inverter.
● Before maintaining the optimizer and PV string, turn o the AC switch and DC
switch. Otherwise, electric shocks may occur as the PV string is energized.
Procedure
Step 1 Turn o the AC switch between the SUN2000 and the power grid.
SUN2000-(3KTL-10KTL)-M1 Series
User Manual 8 Maintenance