Rev 2015-03-02 26
GV10x OPERATION AND SAFETY MANUAL
5.3. Release Procedure
When the GV10x is ready to return to service, properly release it from the isolated state.
5.3.1. Notify personnel who are affected by the lockout/tagout that the GV10x is in the
process of being re-energized.
5.3.2. Check the area to make sure it is safe to restart the GV10x.
5.3.3. Remove the lockout and tag.
5.3.4. Restore AC power to the Controller by toggling the AC line switch at the power
inlet at the back of Controller to the ON (1) position or by restoring power delivered by
the host equipment.
5.3.5. Verify the power is on and the GV10x is operational.
5.3.6. Notify the affected personnel that the GV10x is back in service.