LanTEK III 161809 Iss 2
User Manual Page58
Chapter 6. Structured Cabling Testing
6.1 Test Setup for Single Test Analysis
• Perform calibration if LanTEK
®
II Cable Tester has not been calibrated during the last
7 days.
• Select cable type.
• Separate cable line to be tested from all network components.
• Connect adapter and patch cord to Display handset (DH) and Remote handset
(RH).
• Connect patch cord of display handset (DH) to one end of the cable line and the
patch cord of remote handset (RH) to the other end.
6.2 Test Run of Single Test Analysis
When performing an analysis test, the following sequences are initiated:
• If test requires Remote handset (RH), the Display handset (DH) initially attempts to
establish a connection to the Remote handset (RH). If connection cannot be
established, the Display handset (DH) will show the message "Searching for Remote
(RH). The search is continued until the analysis test is manually cancelled or the
Remote handset (RH) is located.
• After connection to the Remote handset (RH) has been successfully established, its
serial number is read out to check if current configuration data are available. If
during the last 7 days no calibration has been performed on the identified Remote
handset (RH), the user receives a message that calibration is recommended.
• Display handset (DH) continues the selected single test if serial number is valid.
• If test does not require a Remote handset (RH), the Display handset (DH) performs
the test and displays the result.
• Once test is completed, the results can be displayed or printed.
6.3 Perform Single Test Analysis
1. Connect Display (DH) and Remote (RH) handset to cable line that is to be tested.
2. Open "Analyze" on start screen.
3. The tests available for the selected cable type are displayed.
4. Use Arrow Keys to navigate to desired test.