31
8 Commissioning
Liquids
(1)Transmitter
(2)Shut-off fitting
2A shut-off valve to process
2B shut-off valve for test connection or vent screw
(3)Pressure line
(4)Shut-off valve
(6) Blow-down valve
Pressure
application
Initial state: all valves closed
Operate shut-off fitting in the following order:
✱
Open shut-off valve (2B).
✱
Apply a pressure that corresponds to the measurement start to the
transmitter, via the test connection of the shut-off fitting (2).
✱
Check measurement start and correct it, if required
➩
"Output current, measurement start and end", page 38.
✱
Close shut-off valve (2B).
✱
Open shut-off valve (4) on the pressure tapping.
✱
Open shut-off valve (2A).