© KEB Antriebstechnik, 2002
All Rights reserved
Initial Start-up Start-up
Section PageDate Chapter
7.2.1 Switching on of
KEB COMBIVERT
7.2 Initial Start-up
After all preparatory measures have been carried out the KEB COMBIVERT F5 can
be switched on.
The sequence of the switch-on procedure as shown below refers to supplied units
with factory setting. Because of the multitude of programs we cannot take into
consideration customer-specific adjustments.
Picture 7.2.1 Swtich on of KEB COMBIVERT
Ye s
Ye s
Ye s
1. Check mains voltage
2. Operator inserted
correctly?
3. Check connection of
control card for short
circuit
Switch on inverter
Display dark ?
Is an
error message
displayed ?
(E.xx)
Look up cause and remedy in
chapter 9 „Error Assistance“
Display „noP“ ?
Switch control release
Press „FUNCT“-key
Display „CP.1“
check the default
configuration