Maintenance
06-237619-001 6-3 April 2020
As an Authorized Kidde IGS Distributor, perform preventative maintenance per Table 6-2.
Table 6-2. Authorized Kidde Fire Systems Distributor Preventive Maintenance Schedule
Schedule Requirement Paragraph
Semi-Annual Perform Monthly inspection as outlined in Section 6-5
and the following additional tasks:
Check lockout valves Section 6-6.1
Check actuators on selector valves Section 6-6.2
Check distribution pipework and nozzles Section 6-6.3
Inspect the protected room Section 6-6.4
Test pressure switches Section 6-6.5
Test release units Section 6-6.6
Test Nitrogen Pilot Control Heads (if applicable) Section 6-6.7
Inspect Flexible Hoses Section 6-6.8
Verify Odorizer Assembly Section 6-6.9
Annual Perform Semi-Annual inspection as outlined in Section 6-6
and the following additional tasks:
Check Kidde IGS System Cylinder Pressure Gauges Section 6-7.1
Every 2 Years Perform Annual inspection as outlined in Section 6-7
and the following additional tasks:
Blow out distribution piping Section 6-8.1
Every 5 Years (CFR) Perform 2 year Inspection as outlined in Section 6-8
and the following additional tasks:
Agent cylinder hydrostatic pressure test and/or inspection
Section 6-9.1
Nitrogen pilot cylinder hydrostatic pressure test and/or inspection Section 7-6.1
Flexible hose hydrostatic pressure test and inspection Section 6-9.2
Every 10 Years (EU) Perform 2 year Inspection as outlined in Section 6-8
and the following additional tasks:
Agent cylinder hydrostatic pressure test
Section 6-10.1
Nitrogen pilot cylinder hydrostatic pressure test Section 7-6.1