11.3 Finalizing the commissioning (MRL elevators)
Step Action Illustration/Note
1 Remove all the tools and waste material
from the work site.
2 Clean the site.
3 Return the elevator to normal.
Perform a test run for the elevator.
If the load weighing device is not working
correctly, make adjustment according to
APPENDIX B.
4 Return the elevator to service.