V - 8
Working with the Big Pack Baler
5.5 Emptying the Bale Channel
The maintenance platform may only be mounted when the machine is at a standstill. Switch off
the engine and remove the ignition key. Apply the flywheel brake.
The packs in the bale channel should be bound before
emptying the bale channel. To do this initiate the bin-
ding process manually (see chapter 5.4.4 "Initiating the
Binding Process Manually").
Open the bale channel from the control and indicator
box. The procedure is thoroughly described in chapter
4.6.2 "Opening the Bale Channel".
Actuate the pack ejector (1) with the double action
control boxes and transport the big pack out of the bale
channel.
Always return the bale ejector to the
front position after ejecting the big pack.
BP380-7-052
1
1