12.1 Checklist for commissioning and inspection
Table59: Checklist for commissioning and inspection
Action OK
Read the operating instructions. □
Check power supply. □
Compare the power supply data against the name plate data. □
Carry out tests to DIN VDE 0100-610. □
Check the direction of rotation. □
Check automatic switching:
- Pump changeover
- Additional start-up of the stand-by pump at peak load
- Start-up of the stand-by pump should the duty pump fail
□
□
□
If available: Check settings on motor protection relay. □
Check the current input of the pump. □
Check the changeover time from star to delta: required = approx. 3 seconds up to 22kW power. □
Thermal circuit breaker connection:
- Ensure that inputs/outputs and serial interface are galvanically isolated from the thermal circuit
breaker inputs.
- If the thermal circuit breaker has no safe isolation from the low-voltage mains, decouple the
signals via coupler modules (accessories).
□
Check correct assignment to pump. □
Re-tighten the pump terminals. □
Check the switching mechanisms. □
Check the start and stop levels. □
Check messages for correct function and effect. □
Determine the spare parts requirements, if any. □
Train operating personnel. □
Provide new operating manual if necessary. □