Commissioning
Before switching on
7
l 38
LDEDS−CCU210B EN 4.0
7 Commissioning
7.1 Before switching on
Before initial switch−on, check ...
ƒ ... whether the drive is undamaged.
ƒ ... the entire wiring with regard to completeness, short circuit and earth fault.
ƒ ... whether the mains and the motor are connected in correct phase relation.
ƒ ... whether the control bars and message bars are connected in correct phase
relation.
ƒ ... whether the configuration saved is valid for the application.
ƒ ... whether the parameters loaded are optimally adapted to the motor.