Heavy load lattice extension
6.2 Rigging the heavy load lattice extension
Lattice extension operating instructions 3 112 441 en 6 - 7
GMK 4100/4100-L/5095
11.01.2008
Pull the pins (4) out of the holder (6).
Attach the heavy load lattice extension with
the pins (4) to the left side of the main boom
head and secure them with retaining pins.
Insert the pin (1) into the bearing point (2)
and secure it with a retaining pin.
Pull the pin out of the bearing point (3).
Swivel the heavy load lattice extension onto the main boom until the
bearing points (1) and the boreholes align.
Pull both pins (4) out of the holder (5).
Insert both pins (4) in the bearing points (3)
on the right side of the main boom head and
secure them with retaining pins.
Insert the pin (1) into the bearing point (2)
and secure it with a retaining pin.
The heavy load lattice extension is now in
working position.
Reeve the hook block; à Attaching and