NEC PASOLINK installation procedure
January 2002
Before going to site check list
Before going to any site, please be sure you completely prepared the following items:
1- The installation tools.
2- The test equipment ,materials ,and tools.( for test work only)
3- Site installation drawings.
4- All labels/stickers (hard and soft copy)
5- Frequency plan and system configuration documents.
6- Test procedure and test data sheets .( for test work only)
7- Confirm access to site/station.
8- Check the condition of the vehicle to be used.
9- Make sure you and your staff are in good conditions (physically)
10- Confirm the site/station entrance conditions.
11- Arrive to site/station safely.
Notes:
1- The installation tools (per team) include:
Description
Quantity
Tap rule 50 M. 1
Square 150mm x 100 mm. 1
Scriber 1
Level A-type 450 mm. 1
Tester . 1
Wrench set A-type 6-24 mm 2
Adjustable wrench 150 mm 2
Adjustable wrench 250 mm 2
Socket wrench kit 1
Screw driver (-) 150 1
Screw driver (+) NO.3 (150) 1
Straight shank drill set (3.0 – 13.0 mm) 5
Concrete drill set (4.8 – 18.0 mm) 5
Drill bag 2
Electric drill 6.5 mm (230 V) 1
Hammer drill 19 mm (230 V) 1
Point drill 6.4 mm (with holder) 1
Point drill 6.4 mm 1
Center punch 125 mm 1
Hack saw frame 2

Table of Contents