Fehler! Verwenden Sie die Registerkarte 'Start', um Title;Title dem Text zuzuweisen, der hier angezeigt werden soll. |
12 | 04.10.2021 | Page 40
Connect the disinfection pump to the disinfection point.
2.
Open the shut-off valve permeate to the drain.
3.
4.
Start the disinfection pump
The procedure to start the disinfection pump NAC-RO-DP-
UG is described in the respective Operation Manual
Start the device
5.
6.
Check for correct disinfectant concentration at the
permeate outlet with test strips. Use Minncare Test Strips
Indication 1% for this.
Let the disinfection pump run until sufficient disinfectant is
detected.
7.
Close the shut-off valve permeate to the drain.
Switch off the system
9.
Restart the system after 20 minutes.
10.
Open the shut-off valve permeate to the drain.