Startup Procedure and Checklist (Continued)
F Visually inspect the sight glass and record your
observations:
Compressor Sight Glass
Oil Level
(1/4, 1/2, 3/4, Full)
________________
F Record the following readings with your service
tools:
Measured Amps (Main)
______________ L1
______________ L2
______________ L3
______________ Amps
Measured Amps
(Compressor)
______________ L1
______________ L2
______________ L3
______________ Amps
Contactor B
(230V Units Only)
______________ L1
______________ L2
______________ L3
______________ Amps
Measured Amps
(Secondary 120V)
L1______________ Amps
Commissioning Agent
Signature
_________________________
Date
_______ /_______ /________