6.5.16. Regeneration days override
Set the maximum number of days that the valve is in service without regenerating, regardless from
the volume of water used.
Note
For a timeclock valve, this value must be set as regeneration period in days. For metered
valves, it is regenerated once the amount of days is reached at a preset time unless the
meter triggers regeneration before. Calendar override initiate regeneration only if no
regeneration has been initiated within the delay programmed in calendar override
parameter.
6.5.17. Regeneration start time
Set the time for regeneration start.
Mandatory
It must be set when the valve is in timeclock mode or with a calendar override.
AJ Set the trip point 3 delay with , and .
→ Can be adjusted from 30 to 99 seconds.
AK Press to validate the selection and advance to the next
parameter.
TRIP DELAY 3:
30 SECONDS
AL Adjust the number of days with , and .
AM Press to validate the selection and advance to the next
parameter.
→ Can be adjusted from:
1 to 99 days for timeclock regeneration;
OFF to 99 days for metered regeneration.
Without calendar forcing.
REGENERATION DAY
OVERRIDE:OFF
Forcing every 3 days.
REGENERATION DAY
OVERRIDE:03DAYS
AN Adjust the time of regeneration with , and .
AO Press to validate the selection and advance to the next
parameter.
Regeneration at 2:00 am.
REGENERATION
TIME 02:00HR