Pulsar® Precision Operaon and Installaon Manual (Model PS-1HCE) Rev 2.0 04/2022
16
6.1.3 SystemPowerUp
Figure10. Feeder Control Box
INDICATORLIGHTS
Flow(SolidGreen) Feed(SolidGreen) Wash(SolidGreen) Alert(FlashingRed)
Flow switch senses ow in pool
recirculaon piping
Feed solenoid valve is acve Wash solenoid valve is acve High level switch is triggered
(Overow condion)
BUTTONS
Power Mode
Toggle feeder from standby (o) to ready to feed (On) Toggle from Manual (mer mode) to ORP (ORP mode)
Note: ORP light ashes green when chlorine signal is present
To power up the system:
1. Connect the control box to a dedicated AC power source in accordance with the site requirements secon 4.1.1.
2. Aer a 30 sec boot-up period, the box will power up with the indicator lights turning on. Conrm the following indicator lights are on:
Power : red/o.....A red OFF indicator light means the box is powered and on standby.
Mode : green/ORP or MANUAL.....Indicates the last operang mode the control box was in.
Flow : green…..Indicates there is ow in the pool recirculaon piping. If there is no light, there is either no ow in the piping, the
orange ow switch cable is not correctly connected to the ow switch, or the ow switch is bad.
FEED, WASH, ALERT…..O when the power is on O.
3. Slowly open the inlet ball valve to allow water to ow through the manifold.
4. Press the control box power buon to energize the system.
5. Put the control box on manual mode to energize the feed solenoid valve and send water into the hopper.
6. Check for leaks from lines, valves, and connecons. If necessary, ghten parts.
7. Put the control box back on ORP mode.
8. Connect the control box ORP plug to an ORP (chemical controller) chlorine demand output.
9. Use the ORP controller to send a chlorine feed signal to conrm operaon of the Pulsar® Precision control box.
10. When the chlorine signal is removed, verify that the controller goes into four wash cycles of 15 sec On and 15 sec O.
11. Once all operang condions are veried, press the power buon on the control box to put it back into standby.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Pulsar PS-1HCE and is the answer not in the manual?

Pulsar PS-1HCE Specifications

General IconGeneral
BrandPulsar
ModelPS-1HCE
CategorySwimming Pool Filter
LanguageEnglish