Unit assembly
46 © robatherm
Installation temperature must be at least
+10 °C.
Fig. 72: Installation temperature
6. At temperatures below +10 °C,
roofing membranes at the corner
and roofing membrane stripes (G)
must be preheated with hot air.
Fig. 73: Preheating
7. Cut roofing membrane stripes (G)
to size so that they overlap the
already laid roofing membrane by
at least 10 mm.
Fig. 74: Cutting roofing membrane
stripes to size
8. Apply solvent-welding agent with
a flat brush in the area of the hole
the size of the cutting on the
already laid roofing membrane.
Fig. 75: Applying solvent-welding agent