LIFTING THE CRANE FULLY ASSEMBLED
Some shooting locations are hard to accede just rolling the crane in
and require lifting the whole crane without tearing it apart. If it is
necessary to lift the crane, use straps or span sets able to lift the
weight of the crane and pass them under the chassis of the dolly to a
higher support point (fig.10.xx). To do this operation it is better to do it
without remote head and with the arm fully closed and more or less
balanced (to balance it in this position, remove the electronic box and
add weights in the front counterweight support point until it is full).