4. Removing the power unit shield , power/ballast unit and power unit.
9. Remove the seven screws and detach the power unit shield.
10-1. Remove the two screws.
10-2. Remove the four white supports and detach the ballast unit.
11. Remove the four screws and detach the power unit.
11
10-1
10-2
9
Power unit shield
Ballast unit
Power unit
9
11
10-2