EasyManuals Logo

Siemens 1PL618 Series User Manual

Siemens 1PL618 Series
80 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #57 background imageLoading...
Page #57 background image
Maintenance
7.2 Inspection
A5E00215731A AD
Siemens AG Operating Instructions 2.02 1PL618
55
7.2 Inspection
7.2.1 General inspection specifications
Instructions relevant to safety
NOTICE
The required regreasing intervals for rolling-contact bearings (optional) are not the same as
the servicing intervals. They must be observed.
Note
When servicing a three-phase motor, you do not generally need to dismantle it. The motor
only has to be dismantled if the bearings are to be replaced.
[ID: 366]
7.2.2 Initial inspection
Inspection interval for initial inspection
The initial inspection once the three-phase motor is assembled and commissioned is, under
normal circumstances, conducted after approx. 500 operating hours, but at the latest after 6
months.
Conducting the initial inspection
While the motor is running, check that:
the equipment conforms to the stated electrical characteristics.
the smooth running characteristics and motor noise during operation have not
deteriorated.
When the motor has been shut down, check that:
the motor foundation has no indentations or cracks.
Correct any deviations that are determined in the inspection without delay.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens 1PL618 Series and is the answer not in the manual?

Siemens 1PL618 Series Specifications

General IconGeneral
BrandSiemens
Model1PL618 Series
CategoryController
LanguageEnglish

Related product manuals