Commissioning
4.5 Commissioning with STARTER
Inverter with CU240B-2 and CU240E-2 Control Units
Operating Instructions, 07/2010, FW 4.3.2, A5E02299792B AA
77
4.5.5 Creating a STARTER project
If you still do not know STARTER, then we recommend that you commission the system
using the project wizards.
Procedure
● Switch on the inverter supply voltage.
● Launch the STARTER commissioning tool.
● Start a new project via "Project / New with Wizard".
● Click on "Find drive units online ...".
● In the window that follows (not shown here), enter a meaningful name for your project
and click on "Continue". The following dialog box is displayed.
● Click "Change and test..." to set up the PG/PC interface.