Installation
2.2 Forming the Internal Battery
FUP1010 IP67 Portable Quick Start
Operating Instructions, 01/2013, CQO:QSG003 Revision 05
9
Table 2- 1 Power Cord Codes
POWER CORD Assembly P/N
Plug Std. Rating
1015BCA-1 CEE 7/7 10A / 230VAC
1015BCC-1 A5 3112 10A / 250VAC
1015BCD-1 BS 1363 5A / 240VAC
1015BCJ-1 JIS 8303 12A / 125VAC
1015BCK-1 NEM 5-15P 10A / 120VAC
1015BCL-1 SEV 1011 10A / 250VAC
2.2 Forming the Internal Battery
Battery Operation
All portable systems include battery chargers that operate from an AC voltage source. We
strongly recommend that you "form" and charge the battery before operating the system for
the first time.
The Charge Indicator LED
A battery status indicator shows the status of its internal battery and charging circuits. The
indicator LED color switches between red or green based upon the flow meter operation.
LED Battery Condition
Green Trickle charge in progress
Red Rapid Charge in progress (flow meter must be off)
Forming the Internal Battery
The flow meter uses an internal, rechargeable battery pack designed for a rapid charge cycle
(NiMH, 12 VDC, 3200mAH). The batteries have to be "formed" to deliver their optimum
operating time, which is approximately 7 hours. This is accomplished by performing a
minimum of two complete discharge/charge cycles.
Note
To remove, replace or dispose of the internal battery pack refer to Maintenance and Service
section in the instruction manual.