6.9.1 Controller Setup
The following steps should be performed during commissioning:
If required, remove the CPU Card and fit the optional RTC battery backup kit (section
6.9.2)
Load the IC4 configuration (section 6.9.3)
Load the Plus+ Site Layout Configuration (section 6.9.4)
Add the required Licence(s) (section 6.9.7)
If required, configure the communications systems (e.g. IP data) (section 6.9.8)
If required, configure and start MOVA referring to the MOVA7 handbook -
667/HB/31601/000
If required, configure and start UTC referring to the UTMC OTU handbook -
667/HB/46000/004
If required, start the Controller Monitor application to report controller status to
Stratos the application control is found via the web page; Systems
Applications.
Set the controller date and time (section 6.9.11)
Bag all signal heads
Perform Lamp tests to ensure correct configuration (section 6.9.12)
Perform Solar Cell testing (section 6.9.13)
Perform Junction Testing (section 6.9.14)
Extract site information for review with customer (section 6.9.15)
When satisfied with the configuration and operation of the controller, consider
refreshing the latest restore point and retaining it so that this configuration can be
restored if necessary. See the ST950 User Interface Handbook (667/HU/46000/000)
for further information.